|
2008 National
Plumbing &
HVAC Estimator
Chapter Preview
Introduction | Table
of Contents |
Back Cover
How to Use This Book
This 2008 National Plumbing
& HVAC Estimator is a guide
to estimating labor and
material costs for plumbing,
heating, ventilating and air
conditioning systems in
residential, commercial and
industrial buildings.
Inside
the back cover of this book
you'll find an envelope with
a compact disk. The disk has
National Estimator, an easy
to-use estimating program
with all the cost estimates
in this book. Insert the CD
in your computer and wait a
few seconds. Installation
should begin automatically.
(If not, click Start,
Settings, Control Panel,
doubleclick Add/Remove
Programs and Install.)
Select Show Me from the
installation menu and Dan
will show you how to use
National Estimator. When
Show Me is complete, select
Install Program. When the
National Estimator program
has been installed, click
Help on the menu bar, click
Contents, click Print all
Topics, click File and click
Print Topic to print a
40-page instruction manual
for National Estimator.
Costs in This Manual
will apply within a few
percent on a wide variety of
projects. Using the
information given on the
pages that follow will
explain how to use these
costs and suggest procedures
to follow when compiling
estimates. Reading the
remainder of this section
will help you produce more
reliable estimates for
plumbing and HVAC work.
Manhour Estimates in This
Book will be accurate
for some jobs and inaccurate
for others. No manhour
estimate fits all jobs
because every construction
project is unique. Expect
installation times to vary
widely from job to job, from
crew to crew, and even for
the same crew from day to
day.
There's no way to eliminate
all errors when making man
hour estimates. But you can
minimize the risk of a major
error by:
1. Understanding what's
included in the manhour
estimates in this book, and
2. Adjusting the man hour
estimates in this book for
unusual job conditions.
The Craft@Hrs Column.
Manhour estimates in this
book are listed in the
column headed Craft@Hrs.
For example, on page 19
you'll see an estimate for
installing a 6 gallon hot
water heater. In the
Craft@Hrs column
opposite 6 gallon you'll
see:
P1 @.500
To the left of the @ symbol
you see an abbreviation for
the recommended work crew.
Page 7 shows the wage rates
and craft codes used in this
book.
To the right of the @ symbol
you see a number. The number
is the estimated manhours
(not crew hours) required to
install each unit of
material listed. In the case
of a 6 gallon hot water
heater, P1 @ .500 means that
.500 manhours are required
to install 1 hot water
heater.
Costs in the Labor $
Column are based on
manhour estimates in the
Craft@Hrs column. Multiply
the manhour estimate by the
. assumed hourly labor cost
to find the installation
cost in the Labor $ column.
For example, .500 manhours
times $32.55 (the average
wage for crew P1) is $16.28.
Monthly price updates on
the Web are free and
automatic all during 2008.
You'll be prompted when it's
time to collect the next
update. A connection to the
Web is required.
Manhour Estimates
include all productive labor
normally associated with
installing the materials
described. These estimates
assume normal conditions:
experienced craftsmen
working on reasonably well
planned and managed new
construction with fair to
good productivity. Labor
estimates also assume that
materials are standard
grade, appropriate tools are
on hand, work done by other
crafts is adequate, layout
and installation are
relatively uncomplicated,
and working conditions don't
slow progress.
All manhour estimates
include tasks such as:
Unloading and storing construction
materials, tools and
equipment on site.
Working no more than two
floors above or below ground
level. .
Working no more than 10 feet
above an uncluttered floor.
Normal time lost due to work
breaks.
Moving tools and equipment
from a storage area or truck
not more than 200 feet from
the work area.
Returning tools and
equipment to the storage
area or truck at the end of
the day.
Planning and discussing the
work to be performed.
Normal handling, measuring,
cutting and fitting.
Regular cleanup of
construction debris.
Infrequent correction or
repairs required because of
faulty installation.
If the work you're
estimating won't be done
under these conditions, you
need to apply a correction
factor to adjust the manhour
estimates in this book to
fit your job.
Applying Correction
Factors. Analyze your
job carefully to determine
whether a labor correction
factor is needed. Failure to
consider job conditions is
probably the most common
reason for inaccurate
estimates.
Use one or more of the
recommended correction
factors in Table 1 to adjust
for unusual job conditions.
To make the adjustment,
multiply the man hour
estimate by the appropriate
conversion factor. On some
jobs, several correction
factors may be needed. A
correction factor less than
1.00 means that favorable
working conditions will
reduce the man hours
required.
Supervision Expense
to the installing contractor
is not included in the labor
cost. The cost of
supervision and
nonproductive labor varies
widely from job to job.
Calculate the cost of
supervision and
non-productive labor and add
this to the estimate.
Hourly Labor Costs
also vary from job to job.
This book assumes an average
man hour labor cost of
$37.67 for plumbers and
$36.95 for sheet metal
workers. If these hourly
labor costs are not accurate
for your jobs, adjust the
labor costs up or down by an
appropriate percentage.
Instructions on the next
page explains how to make
these adjustments. If you're
using the National Estimator
disk, it's easy to set your
own wage rates.
Hourly labor costs in this
book include the basic wage,
fringe benefits, the
employer's contribution to
welfare, pension, vacation
and apprentice funds, and
all tax and insurance
charges based on wages.
Table 2 at the top of the
next page shows how hourly
labor costs in this book
were calculated. It's
important that you
understand what's included
in the figures in each of
the six columns in Table 2.
Here's an explanation:
Column 1, the base
wage per hour, is the
craftsman's hourly wage.
These figures are
representative of what many
contractors are paying
plumbers, sheet metal
workers and helpers in 2008.
Column 2, taxable
fringe benefits, includes
vacation pay, sick leave and
other taxable benefits.
These fringe benefits
average about 5.15% of the
base wage for many plumbing
and HVAC contractors. This
benefit is in addition to
the base wage.
|
Condition |
Correction
Factor |
|
Work in large open
areas, no partitions |
.85 |
|
Prefabrication under
ideal conditions,
bench work |
.90 |
|
Large quantities of
repetitive work
|
.90 |
|
Very capable
tradesmen |
.95 |
|
Work 300' from
storage area |
1.03 |
|
Work 400' from
storage area |
1.05 |
|
Work 500' from
storage area
|
1.07 |
|
Work on 3rd through
5th floors |
1.05 |
|
Work on 6th through
9th floors |
1.10 |
|
Work on 10th through
13th floors |
1.15 |
|
Work on 14th through
17th floors
|
1.20 |
|
Work on 18th through
21st floors
|
1.25 |
|
Work over 21 floors |
1.35 |
|
Work in cramped
shafts |
1.30 |
|
Work in commercial
kitchens |
1.10 |
|
Work above a sloped
floor |
1.25 |
|
Work in attic space |
1.50 |
|
Work in crawl space |
1.20 |
|
Work in a congested
equipment room |
1.20 |
|
Work 15' above floor
level |
1.10 |
|
Work 20' above floor
level |
1.20 |
|
Work 25' above floor
level |
1.30 |
|
Work 30' above floor
level |
1.40 |
|
Work 35' to 40'
above floor level |
1.50 |
|
Table 1
Recommended
Correction Factors |
|
Column 3, insurance and
employer-paid taxes in
percent, shows the insurance
and tax rate for the craft
workers. The cost of
insurance in this column
includes workers'
compensation and
contractor's casualty and
liability coverage.
Insurance rates vary widely
from state to state and
depend on a contractor's
loss experience. Note that
taxes and insurance increase
the hourly labor cost by
approximately 30%. There is
no legal way to avoid these
costs.
Column 4, insurance
and employer taxes in
dollars, shows the hourly
cost of taxes and insurance.
Insurance and taxes are paid
on the costs in both columns
1 and 2.
Column 5, non-taxable
fringe benefits, includes
employer paid non-taxable
benefits such as medical
coverage and tax-deferred
pension and profit sharing
plans. These fringe benefits
average 4.55% of the base
wage for many plumbing and
HVAC contractors.
|
Column Number |
1 |
2 |
3 |
4 |
5 |
6 |
|
Craft |
Base Wage
per hour |
Taxable
fringe
benefits (at
5.15% of
base wage) |
Insurance
and
employer
taxes (%) |
Insurance
and
employer
taxes ($) |
Non-taxable
fringe
benefits (at
4.55% of
base wage) |
Total hourly
cost used in
this book |
|
Laborer |
19.01 |
0.98 |
32.93% |
6.58 |
0.86 |
27.43 |
|
Plumber |
27.81 |
1.43 |
24.47% |
7.16 |
1.27 |
37.67 |
|
Sheet Metal Worker |
26.92 |
1.39 |
26.21% |
7.42 |
1.22 |
36.95 |
|
Operating Engineer |
27.32 |
1.41 |
25.42% |
7.30 |
1.24 |
37.27 |
|
Sprinkler Fitter |
27.32 |
1.41 |
25.28% |
7.26 |
1.24 |
37.23 |
|
Electrician |
27.25 |
1.40 |
20.04% |
5.74 |
1.24 |
35.63 |
|
Craft Code |
Crew Composition |
Average Hourly
Cost
per Manhour |
|
ER |
4
building plumbers, 2
building laborers, 1
operating engineer |
34.69 |
|
SN |
4
building sheet metal
workers, 2 building
laborers, 1
operating engineer
|
34.28 |
|
P1 |
1
building plumber and
1 building laborer |
32.55 |
|
SK |
4
sprinkler fitters, 2
building laborers, 1
operating engineer
|
34.44 |
|
SL |
1
sprinkler fitter and
1 laborer
|
32.33 |
|
S2 |
building sheet
metal worker, 1
building laborer |
32.19 |
|
BE |
1
electrician |
35.63 |
|
Table 2 labor
Costs Used in This
Book |
|
The employer pays no taxes
or insurance on these
benefits.
Column 6, the total
hourly cost in dollars, is
the sum of columns 1, 2, 4,
and 5. The labor costs in
Column 6 were used to
compute costs in the Labor $
column of this book.
Adjusting Costs in the
Labor $ Column. The
hourly labor costs used in
this book may apply within a
few percent on many of your
jobs. But wage rates may be
much higher or lower in some
areas. If the hourly costs
shown in Column 6 of Table 2
are not accurate for your
work, adjust labor costs to
fit your jobs.
For example, suppose your
hourly labor costs are as
follows:
Plumber $17.00
Laborer $15.00
Total hourly crew cost
$32.00
Your average cost per
manhour would be $16.00
($32.00 per crew hour
divided by 2 because this is
a crew of two).
A labor cost of $16.00 is
about 50% of the $32.55
labor cost used for crew P1.
Multiply costs in the Labor
$ column by .50 to find your
estimated cost.
For example, notice on page
19 that the labor cost for
installing a 6 gallon hot
water heater is $16.30 each.
If installed by your
plumbing crew working at an
average cost of $16.00 per
manhour, your estimated cost
would be 50% of $16.30 or
$8.15 per heater.
Adjusting the labor costs in
this book will make your
estimates much more
accurate. Making adjustments
to labor costs is both quick
and easy if you use the
National Estimator disk.
Equipment Cost will
vary according to need and
application. It typically is
$100 per hour for a 10-ton
hydraulic truck-mounted
crane.
Material Costs in
this manual are intended to
reflect what medium- to
low-volume contractors will
be paying in 2008 after
applying normal discounts.
These costs include charges
for delivery to within 25 to
30 miles of the supplier.
Overhead and Profit
for the installing
contractor are not included
in the costs in this manual
unless specifically
identified in the text.
Markup can vary widely with
local economic conditions,
competition and the
installing contractor's
operating expenses. Add the
" markup that's appropriate
for your company, the job
and the competitive
environment.
How Accurate Are These
Figures? As accurate as
possible considering that
the editors don't know your
material suppliers, haven't
seen the plans or
specifications, don't know
what building code applies
or where the job is, had to
project material costs at
least six months into the
future, and had no record of
how much work the crew that
will be assigned to the job
can handle.
You wouldn't bid a job under
those conditions. And I
don't claim that all
plumbing and HVAC work is
done at these prices.
Estimating Is an Art,
not a science. There is no
one price that applies on
all jobs. On many jobs the
range between high and low
bid will be 10% or more.
There's room for legitimate
disagreement on what the
correct costs are, even when
complete plans and
specifications are
available, the date and site
are established, and labor
and material costs are
identical for all bidders.
No estimate fits all jobs.
Good estimates are custom
made for a particular
project and a single
contractor through judgment,
analysis and experience.
This book is not intended as
a substitute for judgment,
analysis and sound
estimating practice. It's an
aid in developing an
informed opinion of cost,
not an answer book.
Additional Costs to
Consider
Here's a checklist of
additional costs to consider
before submitting any bid.
1. Sales taxes
2. Mobilization costs
3. Payment and performance
bond costs
4. Permits and fees
5. Storage container rental
costs
6. Utility costs
7. Tool costs
8. Callback costs during
warranty period
9. Demobilization costs
Exclusions and
Clarifications
Neither the job
specifications nor the
contract may identify
exactly what work should be
included in the plumbing and
HVAC bid. Obviously, you
have to identify what work
is included in the job.
The most efficient way to
define the scope of the work
is to prepare a list of
tasks not normally performed
by your company and attach
that list to each bid
submitted. Here's a good
list of work that should be
excluded from your bid.
Your Bid Should Exclude
Final cleaning of
plumbing fixtures
Backings for plumbing
fixtures
Toilet room accessories
Electrical work, including
motor starters
Electrical wiring and
conduit over 100 volts
Temporary utilities
Painting, priming and
surface preparation
Structural cutting, patching
or repairing
Fire protection and
landscape sprinklers
Equipment supports
Surveying and layout of
control lines
Removal or stockpiling of
excess soil
Concrete work, including
forming and rebar
Setting of equipment
furnished by others
Equipment, unless shown, and
personnel hoisting
Wall and floor blockouts
Pitch pockets
The costs of performance or
payment bonds
Site utilities
Asbestos removal or disposal
Contaminated soil removal or
disposal
Major increases in copper
material prices
Fire dampers not shown on
the plans
Your Bid Should Include
Trash sweep-up only.
Others haul it away
Site utilities from building
to property line only
Piping to 5 feet outside the
building only
Plumbing & HVAC permits for
your work only
Beware of Price
Changes
There's no way to be sure
what prices will be in three
to six months. All labor,
equipment, material and
subcontract prices in a bid
should be based on costs
anticipated when the project
is expected to be built, not
when the estimate is
compiled. That presents a
problem. Except for the
installation of underground
utilities, most plumbing and
HVAC work is done six months
to a year after the bid is
submitted. When possible,
get price protection in
writing from your suppliers
and subcontractors. If your
suppliers and subs won't
guarantee prices, include an
escalation allowance in your
bid to cover anticipated
price increases.
Material Pricing
Conditions
All equipment and material
prices quoted by your
vendors will be conditional.
They usually don't include
sales tax and are subject to
specific payment and
shipping terms. Every
estimator should understand
the meaning of common
shipping terms. They define
who pays the freight and who
has responsibility for
processing freight-damage
claims. Here's a summary of
important conditions you
should understand.
F.O.B. Factory (Free
On Board at the Factory):
Title passes to the buyer
when the goods are delivered
by the seller to the freight
carrier. The buyer pays the
freight and is responsible
for freight-damage claims.
F.O.B. Factory F.F.A.
(Free On Board at the
Factory, Full Freight
Allowed): The title passes
to the buyer when the goods
are delivered by the seller
to the freight carrier. The
seller pays the freight
charges, but the buyer is
responsible for
freight-damage claims.
F.O.B. (city of
destination) (Free On
Board to your city): The
title passes to the buyer
when the goods are delivered
by the seller to the freight
terminal in the city, or
nearest city, of
destination. The seller pays
the freight and is
responsible for
freight-damage claims to the
terminal. The buyer pays the
freight charge and is
responsible for
freight-damage claims from
the terminal to the final
destination.
F.O.B. Job Site (Free
On Board at job site, or
contractor's shop): The
title passes to the buyer
when the goods are delivered
to the job site (or shop).
The seller pays the freight
and is responsible for
freight-damage claims.
F.A.S. Port [of a
specific city] (Free
Alongside Ship at the
nearest port): The title
passes to the buyer when
goods are delivered to the
ship dock or port terminal.
The seller pays the freight
and is responsible for
freight-damage claims to the
ship dock or port terminal
only. The buyer pays the
freight and is responsible
for freight-damage claims
from the ship dock or port
terminal to the designated
delivery point. Obviously,
it's to your advantage to
instruct all vendors to
quote costs F.O.B. the job
site or your shop.
Reducing Costs
Most construction
specifications allow the use
of alternative equipment and
materials. It's the
estimator's responsibility
to select the most
cost-effective products.
Research and compare your
costs before making any
decisions. Avoid selecting
any material or equipment
simply because that's what
you've always done.
Don't recommend plastic
products such as ABS, PVC,
or polypropylene pipe or
corrugated flexible ducts
until you've checked local
code requirements. Most
building codes prohibit use
of these materials inside
public buildings such as
schools, care centers and
hospitals.
It's wise to select 100%
factory-packaged equipment.
Beware of equipment labeled
"Some assembly required"
Field labor costs for
mounting loose coils, motors
and similar equipment are
very high.
Value Engineering
Let's suppose you've
submitted a combined
plumbing and HVAC bid for
$233,000. Your cutthroat
competitor put in a bid at
$4,000 less, $229,000.
Obviously there's no way
you're going to get the job.
Right?
Not so fast! Maybe value
engineering can help you win
that contract - while
fattening your profit
margin.
Suppose the proposal you
submitted had two parts.
Part I is the bid for
$233,000, based entirely on
job plans and specs, just
the way they were written.
But appended to your
proposal is Part II, a list
of suggestions for saving
money without sacrificing
any of the capacity or
quality designed into the
system. Here's an example of
what might be in Part II:
1. Deduct for providing pipe
hanger spacings per UPC in
lieu of specified spacings:
$1,750.00
2. Deduct for reducing
heating hot water pipe sizes
by using 40 degrees F Delta
T in lieu of specified 20
degrees F Delta T: $4,600.00
3. Deduct for providing
pressure/temperature taps at
air handling units, pumps
and chillers in lieu of
specified thermometers and
pressure gauges: $875.00
4. Deduct for eliminating
water treatment in closed
piping systems: $1,800.00
5. Deduct for piping chilled
and heating hot water pumps
in parallel in lieu of
providing 100% standby
pumps: $2,900.00
Total deductions:
$11,925.00
Adopting these suggestions
would make you low bidder by
nearly $8,000. A saving like
that will be tempting to
most owners, especially if
the owner understands that
your suggestions result in a
system that is every bit as
good and maybe better than
the system as originally
designed.
You're not offering to
undercut the competition.
Far from it. You're using
knowledge and experience to
create better value for the
owner. That's called value
engineering and it's likely
to win the respect of nearly
all cost-conscious owners.
Notice that reducing costs
is only part of what value
engineering is all about.
You don't cut costs at the
expense of system quality,
integrity, capacity or
performance.
Don't waste your time, and
your client's, by offering
to substitute cheaper or
lower-quality fixtures or
equipment. Any cutthroat
contractor with a price list
can do that. Recommend the
use of inferior materials
and you'll be associated
with the inferior goods you
promote. Some owners
consider even the suggestion
to be insulting.
The recommendations you make
(like most of those in the
example) will require design
changes. You can expect to
be examined (or even
challenged) on these points.
Be ready to explain and
defend each of your
suggestions. Convince the
client (or the design
engineer) that your ideas
are based on sound
engineering principles and
you're well on the way to
winning the owner's
confidence and the contract.
Now, let's go back to the
list and see how we might
justify the five value
engineering recommendations.
1. Pipe Hanger Spacing.
The pipe hanger spacings
recommended in the Uniform
Plumbing Code (UPC) are
calculated by experienced,
professional structural
engineers. The safety
factors used in these
calculations are very
conservative. They've been
widely used for many years
and have proved to be more
than adequate. There's no
need for more hangers than
the UPC requires.
2. Changing HHW Delta T.
In hydronic heating systems,
heat measured in Btus is
pumped to terminal units.
The proposed change of the
Delta T, from 20 degrees F
to 40 degrees F, has no
effect whatsoever on how
many Btus the system
delivers. You're not
changing anything but the
volume of water being
pumped. At lower volume
levels, the size of the
pump, the pipe and the pipe
insulation can all be
reduced. Not one of these
changes will affect the
system's ability to transmit
heat. Furthermore, operating
costs will also drop, since
less pump horsepower will be
needed to run the smaller
pump.
3. Thermometers/Pressure
Gauges. Thermometers and
pressure gauges installed on
or near vibrating machinery
have a very short life
expectancy. Gauges quickly
lose accuracy under harsh
conditions. Readings will
become less and less
reliable.
That's potentially
dangerous. You can avoid
this problem by using
insertion-type
pressure/temperature taps
instead. Store these
sensitive gauges in a desk
drawer or a tool crib when
not in use. Safely stored,
they're protected from
damage. They'll give
accurate readings longer and
won't need to be replaced as
often. And they're simple to
use. Just insert a gauge in
one of the conveniently
located taps. Make the
reading, then remove the
gauge and put it away.
4. Water Treatment.
ITT Bell & Gossett has done
studies on corrosion in
closed hydronic systems that
have a make-up water rate of
no more than 5% per year.
These studies show that
corrosion virtually stops
when entrained air is either
removed or depleted. No
water treatment is needed in
this closed system.
5. 100% Standby Pumps.
Two pumps piped and operated
in parallel are more
economical. Even if one pump
fails, the other pump can
maintain delivery at 75 to
80% of the designed flow
rate. That's usually
adequate for emergency
operation.
These cost-saving ideas are
small, but could tip the
balance in your favor. I
hope they demonstrate the
potential that value
engineering has when bidding
jobs. Any time you're
compiling an estimate, keep
an eye out for ways to save
money or reduce the owner's
cost. Jot a note to yourself
about each potential saving
you identify. Before
submitting the bid, make a
list of your alternate
suggestions. Maybe best of
all, markup on your value
engineering suggestions can
be higher than your normal
markup. If value engineering
can cut costs by $10,000,
maybe as much as $4,000 of
that should end up in your
pocket!
Value Engineering:
Surplus Materials
Value engineering doesn't
begin and end with job plans
and specs. Value engineering
means getting the most value
at the least cost, no matter
whether it's value to the
owner or value to the
contractor. Smart mechanical
contractors learn to build
extra value into their jobs
by controlling shrinkage of
materials. Nearly every
significant plumbing and
HVAC job ends with at least
some surplus material on
hand. Material left over
when the job is done tends
to be discarded as waste or
hauled off the job in the
back of a truck that doesn't
have your company name on
the door. And why not? It's
surplus - not needed. The
owner didn't need it. So now
it's up for grabs.
Not quite. Let's consider
who actually owns that
surplus material. When your
company has been paid, every
piece of material your crew
installed belongs to the
building owner. But what
about those fittings,
hangers and valves delivered
to the job site but never
actually used? Almost
certainly, those materials
were included in your bid.
So aren't they the property
of the owner? Not in my
opinion. The owner
contracted for a mechanical
system and (presumably) has
one. Unless it's a cost-plus
job or a labor-only job, the
owner didn't buy materials
delivered to the job site.
The owner bought a
mechanical system and has
one - completely separate
and apart from any surplus
materials. In my mind, the
property owner has no more
claim to left-over materials
than the same owner would
have claim to labor hours
not expended or equipment
not used on the same job.
Unless there's some
provision in your contract
to the contrary, surplus
material belongs to the
installing contractor. But
your right to that material
and the chance of actually
getting it back to your shop
are two very different
propositions. I see recovery
of surplus material as a
training issue. As a matter
of company policy, make it
clear to your crews that
surplus material belongs to
your company. The supervisor
on every job should be
accountable for recovery of
excess material. Every
significant job will have at
least some surplus.
Accounting for that surplus
should be part of your
routine close-out procedure.
Fortunately, it's not
difficult. I'll explain.
Control of surplus materials
begins with a good
checklist, or form. I
recommend the Materials,
Equipment and Tool form,
"MET" for short. A blank MET
form appears following this
section. Your MET should
show both what's delivered
to the job site (material,
equipment and tools) and
surplus & drops returned to
your shop at project
close-out. A MET ensures
that the estimator, the shop
inventory manager and your
field supervisor are on the
same page. Your MET
establishes accountability.
Nothing falls through the
cracks. Job input equals job
output plus returns.
Everything delivered to the
job and not expended should
be returned to your shop.
Here's how it works:
1. Based on the estimate
that won you the job, the
items needed are purchased
for the job and staged for
delivery to the job site.
2. As materials, equipment
and tools are delivered to
the job site, your
supervisor completes the
first three columns of the
MET form: Description,
Quantity and Date.
3. As work is completed, the
same supervisor completes
the four columns under
Returned to Inventory:
Quantity Returned, Date,
Status Code and Value. The
status code will be either
"RS" (Returned and Salvaged)
or "RN" (Returned New).
4. Back at your shop, both
RS and RN materials should
be restored to inventory.
5. If your company has an
inventory manager, have that
manager assign the return
value to each item returned.
If you're using QuickBooks
Pro, the "Adjust Inventory"
feature can handle this task
quite easily. Add two new
categories under "Inventory
Stock on Hand by Vendor:'
The first new category is
Returned Salvage. The second
is Returned New. Be sure the
value of RS materials
includes the cost of any
reconditioning done to
restore salvaged materials
(such as pumps and boilers)
to serviceable condition.
6. Comparing MET deployed to
the job site with MET
returned to inventory yields
MET actually used on the
job. That's a very important
number to every plumbing and
HVAC estimator. Be sure
actual usage gets entered on
the Project Summary form.
7. When the take-off on your
next estimate is complete,
compare that materials list
with a summary of RS and RN
materials on hand from prior
jobs.
8. Evaluate which returned
materials can be redeployed
on the new job.
9. It's a management
decision to either (1)
charge the new job for the
cost of RS and RN materials
already on hand, or (2)
consider materials on hand
as "free" and a competitive
advantage in winning the new
bid. Either way, RN and RS
materials are an asset to
your company.
Plumbing and HVAC materials
are expensive. Every
mechanical contractor has an
interest in MET tracking.
Everyone in your company
should be aware of the need
for good materials
management. Used correctly,
the MET form in this book
can help engineer more value
into your jobs.
Maximizing the Value
of Old Estimates
There should be two profits
in every job. The first is
money in the bank - a return
on time and expenses.
The second is what you learn
from the job - primarily by
comparing the estimate you
made with what turns out to
be your actual cost. On some
jobs, the value of lessons
learned may outweigh net
revenue.
Every plumbing and HVAC
contractor has marginal
jobs. That's normal. What
shouldn't be normal is
repeating mistakes. The best
way to avoid trouble in your
future is to keep track of
your past. Keeping old
estimates available for
reference can help prevent
errors on new estimates.
As your file of completed
estimates grows,
organization becomes more
important. You need an easy
way to find similar projects
with the same components and
comparable scope of work. If
your estimating file is in
QuickBooks Pro, searching by
keyword may be enough.
Otherwise, I recommend
creating a short summary for
each completed job, and an
index that references all
summaries available for
comparison. You'll find a
blank Project Summary form
at the end of this section.
To make reference easier,
create an index by type of
job and equipment used. You
may choose to use an
alphabetical index based on
client name or project 10.
How to complete the Project
Summary form is obvious. The
many ways to use this form
may not be so obvious, so
here are a few pointers.
1. Use your index of Project
Summary forms to find
completed jobs most similar
to the job you're bidding.
Believe it or not, Project
Summary forms with the
widest margin of error will
be most useful. Ask
yourself: Who worked on
those projects? Who was the
field superintendent? Who
were the vendors? Did the
errors result from poor
estimating or the poor
performance of vendors,
supervisors or crews? The
most common estimating
errors occur when (a)
inspecting the job site, (b)
examining the plans or (c)
reading the specifications.
What did you miss and why?
Look for pitfalls to avoid
in the job now being
estimated. Identify the
biggest two or three
mistakes made when bidding
that job. Make a notation
about each on the Project
Summary form.
2. Now look at your bid for
the current job. Which
mistakes made on a prior job
might you expect on this
job? Concentrate on the big
three oversights to avoid:
Inspecting the job site;
examining the plans; and
reading the specifications.
3. Unless there's a major
error in take-off, your
estimate of material costs
should be within about 5
percent of the actual costs
of materials. However, it's
common for labor cost
estimates to vary 20 percent
or more from actual labor
costs. This is precisely
where data from old jobs
comes in handy. If your
Project Summary files show
that some project types are
consistent money-losers,
either shift your company's
focus to another class of
work, factor more
contingency into your bids,
or find some way to wring
inefficiencies out of the
labor component. Poor
staging, delivery and
retrieval procedures drag
down labor productivity on
any job. .
4. Use your file of Project
Summary forms to spot any
common thread that runs
through either money-making
jobs or money-losing jobs.
For example, if the names of
certain subcontractors or
vendors are prominent on
low-margin jobs, maybe
there's a relationship
between your profit margin
and choice of subs and
suppliers. Even the best and
most reliable vendors can
become complacent if not
challenged occasionally.
5. Project Summary forms
should note changes and
extras identified after the
contract was signed both for
which your company was paid
and changes done without
additional compensation.
Projects with changes and
extras that exceed about 4
percent of the contract
price deserve special
scrutiny. Jobs with changes
beyond about 4 percent
aren't good for business, at
least in my opinion. Nearly
all changes have a negative
impact on your job schedule
and require a
disproportionate investment
of management resources. Too
many changes can antagonize
the owner and design staff,
even if they were
responsible for the altered
plans. You may know of a
mechanical contractor with a
reputation for capitalizing
on change orders. But I've
rarely seen a job plagued
with changes that turned
into a money-maker for
anyone - except the
attorneys. Your file of
Project Summary forms will
show job types that carry
change order risk. Before
finalizing and submitting
any bid, consider whether
the job will get mired in
disputes over changes and
extras. If similar jobs have
ended on the courthouse
steps, factor that risk into
your estimate.
Utility of a Project Summary
forms file is limited only
by your ingenuity. The
important point is to keep
and organize the source of
your second profit available
on every job. What you learn
can be more valuable than
what you earn.
The Estimating
Procedure
Every plumbing and HVAC
estimator works under
deadline pressure. You'll
seldom have the luxury of
spending as much time as you
would like on an estimate.
Estimators who aren't
organized waste valuable
time and tend to make
careless errors. Try to be
well organized and
consistent in your approach
to estimating. For most
projects, I recommend that
you follow the procedures
listed below and in the
order listed:
1. Get a second set of
project drawings and
specifications for use by
your suppliers and
subcontractors. Remember
that your subs and suppliers
need access to the plans and
specs and time to prepare
their quotes.
2. Study the plans and specs
carefully. Highlight
important items. Make a list
of specific tasks that
require labor unit
correction factors. The
estimate is never complete
until you're totally
familiar with the project
and the applicable
construction codes.
3. Get the general
contractor or owner to
identify the proposed
construction schedule and
subcontractor lay-down
(storage) area. Work
schedule and site conditions
always affect your costs.
4. Contact all potential
suppliers and subcontractors
as early as possible. Set a
time when each can come to
your office to make their
take-offs from the spare set
of contract documents.
When this important
preliminary work is done, or
in progress, it's time to
begin your detailed
take-off.
Guidelines for Good
Estimating
You can compile
estimates on a legal pad, a
printed estimating form or
on a computer. Regardless of
the method, these guidelines
will apply:
List Each Cost Separately
on your take-off sheet.
Don't combine system
estimates, even if the
materials are the same type.
A combined system estimate
may have to be completely
redone if materials for one
system are changed at a
later date. Use the Estimate
Detail Sheet on page 16 if
you don't already have a
good material take-off form.
Use Engineer's
Identification Numbers
when listing equipment. The
word pump without any other
description is ambiguous
when there are several pumps
included in the project.
Don't Forget Labor
Adjustment factors if
your labor costs are
significantly higher or
lower than the costs used in
this book. See instructions
on page 7 for adjusting
labor costs.
Use Colored Pencils
or highlighters to mark the
items you've taken off and
listed. Use a different
color for each piping or
ducting system.
Log Telephone Quotes
and other important phone
conversations on a telephone
quote form. See the sample
on page 18.
Project Estimated Costs
for labor, material and
equipment to the time when
the work is expected to be
done, not when the job is
being estimated.
The only good estimate is a
complete estimate.
You've probably heard this
saying, "He who makes the
most mistakes is likely to
be low bidder, and live to
regret it."
Preparing the Proposal
It's both common courtesy
and good business practice
to deliver an unpriced copy
of your bid or proposal
letter to the general
contractor three or four
days before the bid deadline
date. This gives the
contractor time to study
your proposal and obtain
alternate pricing for items
you may have excluded. To
avoid misunderstandings,
make sure your proposals
include, as a minimum, the
following elements:
1. The complete name and
address of the proposed
project.
2. Specification title and
issue date.
3. A complete listing of
drawings and their issue or
revision date.
4. A complete list of
addenda and their dates of
issue.
5. A list of specification
section numbers covered by
your proposal.
6. A list of exclusions,
clarifications and
assumptions.
Your final bid can be phoned
in or sent by fax, but it
should reach the general
contractor or owner no more
than five or ten minutes
before the bid deadline.
Prices submitted too early
may have to be revised
because of last-minute price
changes by subcontractors or
suppliers.
-
We will stop the
chapter sample here on
page 13. The remaining 6
pages of this chapter
consist of a "MET"
Worksheet, Project
Summary form, Estimate
Detail Sheet, Quotation
Sheet, and Record of
Telephone Conversation
form.
|
|
|
Introduction | Table
of Contents |
Back Cover
2008 National Plumbing
& HVAC
Estimator
|
|
|